The Project

Concourse T North Extension at Hartfield-Jackson Atlanta International Airport.
The scope of this project will consist of construction of five additional Airplane Design Group III capable gates to the north end of the concourse. The improvements will extend the concourse in a "J" configuration parallel to Taxiway V and will displace several airside and landside facilities.

The displaced facilities to be included in the enabling phase, include relocation of the north parking deck exit toll plaza, the parking office, a major portion of the north terminal exit road and utilities, the Georgia Power main feed and transformers, the Delta Ground Support Equipment (GSE) facility and Fire Station #32.

Project scopes include, but are not limited to, the following:

  • - Site prep and utilities
  • - Roadway relocation
  • - Toll Booths
  • - Parking Lot Reconfiguration and Improvements
  • - Structural
  • - Architectural
  • - Tenant Improvement
  • - Core and Shell